Contracts on the construction of the underground section from the Mladost I quarter to the Business Park in the Mladost IV quarter signed

2 April 2013 A+AA-
Contracts on the construction of the underground section from the Mladost I quarter to the Business Park in the Mladost IV quarter signed

After the conducting of an open procedure under the Public Procurement Act for the selection of contractors for the Project on the extension of the Sofia Underground, Stage III, Lot 2, section from Underground Station 13 (Mladost I, km 15+450) to Underground Station 16 (Business Park in Mladost IV, km 18+070), the following contracts have been signed for the two separate positions:

On 29 March 2013 METROPOLITEN EAD and MetroBuildMladost alliance signed a contract on the construction of Separate Position No. 1, section from Underground Station 13 (Mladost I, km 15+450) to km 17+000, with two underground stations. The contact is of 53,899,104.98 leva’s worth (exclusive of VAT). Its subject matter involves design, construction, trial-run and setting into operation of the upper sub-section of the extension of the Sofia Underground.

On 28 March 2013 METROPOLITEN EAD and Geometro B.P. alliance signed a contract on the construction of Separate Position No. 2, section from km 17+000 to Underground Station 16 (Business Park in Mladost IV, km 18+070), with one underground station. The contact is of 31,489,458 leva’s worth (exclusive of VAT).

The two contracts form a part of the Project on the extension of the Sofia Underground, Stage III, Lot 2, section from Mladost I quarter to Business Park, Mladost IV quarter, and will be financed under Priority Axis 3 of Operational Programme Transport 2007-2013 through the European Regional Development Fund and national co-financing. The term of implementation of the contracts is 24 months beginning from their entry into force.

 

 

News

EC allocates 293 million Euro for Plovdiv-Bourgas railway line modernization +

16 November 2018

The European Commission allocated 293 million Euros for the modernization of the railway line between the cities of Plovdiv and Bourgas. The rehabilitation of the 293-kilometer section, which was initiated in the past programing period under Op...

Ivaylo Moskovski: By 2019 Sofia to have 48 km of subway lines with 43 stations +

14 March 2018

The subway is a very good example of an intermodal project and its implementation has been very successful, said the minister of Transport, information Technology and Communications Ivaylo Moskovski during today’s inspection of the works at...

European Commission allocates 451 million Euros for the modernization of Elin Pelin - Kostenetz railway line +

1 February 2018

The European Commission approved the financing of the project for modernization of the railway line Elin Pelin - Kostenetz that amounts to 451 million Euros. Over 51 km of railways and 5 railway stations along the line will be modernized through the...
rss