Sofia Metro Extension Project, Stage I, metro diameter II: section Nadezhda Road Junction (MS 5-II) — Cherni Vrah Blvd. (MS 11-II)

A+AA-

The project was approved by the Managing Authority of Operational Programme Transport 2007-2013 on 09.07.2009 and by the European Commission on 22.09.2009.

Deadline:The project is planned to be concluded on 31.12.2014.

Beneficiary: Metropoliten JSC

Budget: Total value of the project: BGN 741,485,759.78

Grant awarded under OP Transport: BGN 362,207,591.81 including VAT

Sources of granted funds:

- European Regional Development Fund: BGN 307,876,453.04

- National co-funding: BGN 54,331,138.77

- Co-funding by Metropoliten JSC: BGN 379,278,167.97

The project is funded under Priority Axis 3 “Improving the intermodality of passenger and freight transportation” and Operational Programme Transport 2007-2013.

Aim of the project

This project aims to connect the Central Railway Station and the International Bus Station with the central city area and, through the metro, with the large residential districts in the western and eastern areas in the direction of the airport, whereby the number of passengers transported after commissioning the metro stations of stage I will total approximately 90,600 passengers per day, and the total number of passengers after concluding this metro extension project will reach about 295,000 passengers per day.

The project efficiency will be ensured in several directions by achieving the following aims:

  • In addition to fast and efficient transport service for the population, the project implementation will provide a convenient intermodal connection with big transportation hubs such as the Central Railway Station, the Central Bus Station, the airport, and with the national road network in the city's peripheral areas where large buffer parking lots have been provided near the end metro stations with a view to limiting the access of vehicles in the central city area.
  • As of their commissioning the sections under the Sofia metro extension project account for 43.2% of the total length of the metro, and the section “Nadezhda Road Junction (MS 5-II) — Cherni Vrah Blvd. (MS 11-II)” alone accounts for 20.5%.
  • The total number of passenger travels in the sections under the project after their commissioning will be 51,275,200 travels per year, out of which the section “Nadezhda Road Junction (MS 5-II) — Cherni Vrah Blvd. (MS 11-II)” of stage I alone will account for 26,455,200 travels per years.
  • Additional 364 permanent new jobs will be created.
  • By implementing stage I of the metro extension the accessibility to the city transport system will result in:
    • Reducing transportation via ground transport by 2.0 million km per year
    • Reducing the number of vehicles by 82 by virtue of public mass transport lines being closed down or reorganised
    • Relieving traffic with the availability of the metro compared with traffic without the metro — 3%
    • Reducing traffic collisions and accidents through relieving traffic with the availability of the metro
    • Reducing harmful emissions in the atmosphere
    • Reducing noise and vibration levels in the urban environment
    • Travel duration will be reduced by 16 minutes which will result in time savings for citizens

Location

South-Western region, Sofia city, BG 411

 

 

Technical parameters of project

The Sofia Metro Extension Project, Stage I — metro diameter II: section from Nadezhda Road Junction (MS 5-II) — Cherni Vrah Blvd. (MS 11-II) is 6.5 km long and has 7 metro stations, the average distance between them being 912 m.

The main technical parameters of the project are as follows:

  • Constructing 5 underground metro stations, retrofitting and finishing the construction of the two metro stations already built, as well as overall architectural layout of the 7 metro stations:
  • Constructing section tunnels between: MS 5-II ÷ MS 9-II and MS 10-II ÷ MS 11-II with a total length of 4.4 km (including the two turnbacks at the start and end of the track);
  • Retrofitting the metro section between MS 9-II and MS 10-II with a length of 1 050 m.

In addition to the construction works the section includes:

  • Rail track and conductor rail with a length of 6.5 km along double track;
  • Three dispatch management systems — covering the movement, electric power supply, as well as sanitary and technical equipment for a 6.5 km long section;
  • Radio connection system for a 6.5 km long section;
  • Electric power supply system, including 7 traction step-down substations, cable lines for a 6.5 km long section and external power supply of key traction step-down substations;
  • Traffic automation and train speed regulation systems for a 6.5 km long section;
  • Complex audiovisual systems and low current systems for metro operations for a 6.5 km long section.

Project contractors

Contractor: METROPROEKT Ltd.

Contract value: BGN 2,334,000.00 including VAT;

Contractor: TRAM METRO Holding

1. SK-13 TRANSSTROY JSC

2. TRACE GROUP HOLD PLC

Contract value: BGN 8,930,256.70 including VAT

Contractor: KONTROL – 99 Ltd. 

Contract value: BGN 546,110.56 including VAT

Contractor: Consortium METROSTROITELSTVO – 2009

1. STANILOV Ltd.

2. DIMOV COMPANY Ltd.

Contract value: BGN 41,518,833.71 including VAT

Contractor: METRO BUILD Holding

1. SIENIT Ltd.

2. G. P. GROUP Ltd.

Contract value: BGN 64,103,787.91 including VAT

Contractor: METRO BUILD 2010 Holding

1. SIENIT Ltd.

2. GP GROUP Ltd.

Contract value: BGN 25,754,770.78 including VAT

Contractor: Consortium BKS Centre – Balkanstroy:

1. Balkanstroy JSC – Razlog

2. BKS-Centre JSC

Contract value: BGN 21,356,904.02 including VAT

Contractor: METRO BUILD DZZD (DZZD: company under the Law on Obligations and Contracts):

1. SIENIT Ltd. – Plovdiv

2. G. P. GROUP Ltd.

Contract value: BGN 4,798,786.62 including VAT

Contractor: Consortium METROSTROITELSTVO – 2009

1. STANILOV Ltd.

2. DIMOV COMPANY Ltd.

Contract value: BGN 3,458,453.89 including VAT

Contractor: ITA ENGINEERING Ltd.

Contract value: BGN 21,768,640.99 including VAT

Contractor: OBELYA U-BAN Holding:

1. SK-13 TRANSSTROY JSC

2. SK-13 HOLDING JSC

Contract value: BGN 19,776,432.79 including VAT

Contractor: Energoremont - Montaji Holding

Contract value: BGN 32,855,867.06 including VAT

 

YouTube icon Instagram icon google plus icon

News

EC allocates 293 million Euro for Plovdiv-Bourgas railway line modernization +

16 November 2018

The European Commission allocated 293 million Euros for the modernization of the railway line between the cities of Plovdiv and Bourgas. The rehabilitation of the 293-kilometer section, which was initiated in the past programing period under Op...

Ivaylo Moskovski: By 2019 Sofia to have 48 km of subway lines with 43 stations +

14 March 2018

The subway is a very good example of an intermodal project and its implementation has been very successful, said the minister of Transport, information Technology and Communications Ivaylo Moskovski during today’s inspection of the works at...

European Commission allocates 451 million Euros for the modernization of Elin Pelin - Kostenetz railway line +

1 February 2018

The European Commission approved the financing of the project for modernization of the railway line Elin Pelin - Kostenetz that amounts to 451 million Euros. Over 51 km of railways and 5 railway stations along the line will be modernized through the...
rss